Skip to Content

How to Write a Complete Steel Pipe RFQ

James Blue, Piping Materials Specialist

How to Write a Complete Steel Pipe RFQ

A request for quotation is comparable only when every supplier is pricing the same item. When the standard, grade, size, wall, length, coating or certificate is left open, each supplier fills the gap differently and the returned numbers are not bids for one product.

Why quotes drift apart

The usual cause is not a price difference. It is a different item: one supplier prices seamless and another prices welded; one prices a standard wall and another prices a made-to-order wall; one includes inspection and another excludes it. Fill those fields before sending the enquiry and the spread narrows, because the item is finally the same.

The specification block

Give dimensions in the form the mill prices, and give both systems when the drawing uses one and the mill works in the other.

FieldWhat to stateExample
Standard and editionOne governing specificationAPI 5L PSL 2
GradeThe grade inside that specificationX52
Outside diameterIn millimetres, with the nominal size219.1 mm (NPS 8)
WallSchedule and millimetres8.18 mm (Schedule 40)
LengthFixed or random, with the tolerance6 m fixed
EndsPlain, bevelled or threadedBevelled ends
QuantityTonnage and piece countStated per line item

Tolerances belong to the pipe standard, not to the enquiry. If the project needs a tolerance tighter than the standard, say so, because it changes both the price and whether the item can be made at all.

Product pages on this site show how one identity is written out: seamless carbon steel pipe, API 5L Grade B seamless pipe and 5-inch Schedule 40 galvanized pipe. Copy the field structure, not the numbers.

Commercial terms

  • Trade term and named port, from the Incoterms edition the contract uses.
  • Target delivery date, and whether it runs from order confirmation or from drawing approval.
  • Validity period of the quotation.
  • Packing: bundles, end protection, and chloride-free packing for stainless steel.

Documents and inspection

State the certificate type the project requires, commonly EN 10204 3.1 when traceability to the producing mill is needed. State whether a third-party inspection is required, which agency, and who carries the cost. Adding inspection after the price is agreed is the most common cause of a re-quote, because it is a scope change rather than a discount request.

How to compare what comes back

Normalise every quote to the same basis before ranking it. Convert to one trade term, add the testing, packing and documentation charges, and check that each supplier quoted the same wall and the same certificate. An outlier well below the rest usually reflects a thinner wall, a different route or a missing test rather than a keener price.

What to Confirm with Your Inquiry

  • Standard, edition and grade, and the seamless or welded route.
  • Outside diameter and wall in millimetres, with the nominal size and schedule.
  • Length and length tolerance, end finish and coating.
  • Quantity per line item, packing and trade term.
  • Certificate type, third-party inspection agency, and the applicable design code.

The wall article gives the schedule-to-millimetre reading these fields depend on: how to read a pipe wall-thickness schedule.

Frequently Asked Questions

What makes an RFQ comparable?

Every supplier must receive the same standard, grade, size, quantity, delivery and inspection requirements.

Which details most often cause quote errors?

Missing schedule, end finish, length tolerance, coating and certificate requirements commonly change price.

Related Products

View More
Call UsWhatsAppEmailInquiry